Change of Use in Singapore: The URA, JTC, HDB and SCDF Approvals You Need

By REDGUARD Engineering Team 9 November 2026· Updated 13 November 2026
Indoor room undergoing renovation with tools, blueprints and hard hats

Changing what your unit is used for? The URA, JTC or HDB planning approval and the SCDF fire safety approval you need, in order, and what to check before you sign a lease.

If you want to use a unit for something different from its approved use, such as turning an office into a tuition centre or a shop into a café, you usually need two sets of approval: planning approval from URA, JTC or HDB, and SCDF approval for the fire safety plans. You need both before you move in and start operating.

Most change of use problems come from signing a lease first and checking later. A ten-minute check on the approved use before you sign can save months of delay and a lease you cannot use. Renting a shophouse? Our shophouse rental checklist covers the fire safety checks to make before you sign.

What counts as a change of use

A change of use happens whenever the new activity is different from what the premises were approved for. Common examples we see:

  • Office to tuition centre, enrichment school, clinic or gym. Our case study on a costly tuition centre renovation shows what goes wrong when this is missed.
  • Shop to restaurant, café or bubble tea outlet. (Taking over an existing outlet? See do you need an FSC when taking over a restaurant.)
  • Warehouse or factory space to showroom, office or training room.
  • Part of a unit, such as a storeroom turned into a seating area, or a car park area turned into storage.

The change does not have to be the whole unit. SCDF requires prior approval for a change of use of any premises or any part of it.

The two approvals and who gives them

ApprovalWho gives itWhat it checks
Planning or landlord approvalURA for most private premises; JTC for JTC industrial units; HDB for HDB shops and commercial unitsWhether the new use is allowed at that location and in that building
Fire safety approvalSCDF, through plans submitted by a Qualified PersonWhether exits, fire protection and layout are safe for the new use and occupant load
Fire Safety Certificate (FSC)SCDF, after the works are completed and inspectedThat the fire safety works were built to the approved plans

Planning approval and fire safety approval are separate. Getting one does not give you the other. Individual units with a different use must comply with the Fire Code standards and apply for their own FSC. If you are not sure whether your works need one, see do I need an FSC for my shop, restaurant or office.

Step 1: Check the approved use before you sign

For private premises, URA's Enquire on Approved Use of Premises e-service and URA SPACE show a unit's last approved use and what uses are allowed. For JTC and HDB units, the approved use is set out in the tenancy and is checked with the landlord. If the new use already matches the approved use, you may not need planning approval, though fire safety works can still need SCDF approval.

Step 2: Planning or landlord approval (URA, JTC or HDB)

  • URA. For most private commercial and industrial premises, a change of use needs planning permission from URA. URA checks the zoning, its guidelines and how the use fits with neighbouring units. URA states a processing time of generally about 10 working days and a non-refundable S$500 processing fee, and incomplete submissions or consultations with other agencies can make it longer.
  • JTC. For JTC industrial units, JTC's consent is needed for the new use, and the use must fit the industrial allocation of the estate.
  • HDB. For HDB shops and commercial units, HDB must approve the change of trade or use. Skipping it can surface years later, as our case study on an HDB commercial unit audited after renovation shows. For the renovation side, see HDB shop renovation approval and PE-endorsed plans.

If the premises are leased from HDB, JTC or SLA, URA also asks for the landowner's letter of consent with the application.

Step 3: SCDF fire safety plans

A new use often brings a different occupant load and different fire safety requirements. A Qualified Person, a registered architect or Professional Engineer, must prepare and submit the change of use plans to SCDF. SCDF's plan fee for a change of use with no increase in floor area is S$90 per storey.

What usually changes on the plans:

  • Exits and travel distances, especially when a classroom or seating area raises the number of people.
  • Fire alarm, sprinklers, emergency lighting and exit signs for new rooms.
  • Kitchen exhaust and fire suppression when the new use is F&B. Opening a food outlet? See the SFA and SCDF approvals for a food shop licence.
  • Storage arrangements when combustible goods move into a unit.

Do not let the contractor start before the plans are approved. We explain why in renovating before SCDF approval.

Step 4: Works, inspection and the FSC

Your contractor builds to the approved plans. A Registered Inspector then inspects the completed fire safety works and the FSC application goes to SCDF. If the works are substantially complete with only minor items outstanding, SCDF may grant a Temporary Fire Permit so you can occupy the premises, with the FSC following, usually within a maximum of 6 months. Our guide to applying for an FSC online covers this stage. See How long does an SCDF FSC application take? for the step-by-step timeline.

What happens if you skip it

SCDF takes a very serious view of unauthorised change of use. When it finds one, it issues a Notice of Offence and the owner or occupier must either restore the original use or engage a Qualified Person to regularise it. Penalties under the Fire Safety Act include fines of up to S$10,000, jail of up to six months, or both, and up to S$200,000 or 24 months for serious offences. SCDF can also order the premises to close.

Before you sign a lease: a short checklist

  1. Ask the landlord or agent for the unit's approved use, and check it with URA, JTC or HDB.
  2. Write down your intended use, floor layout and expected number of people.
  3. Ask whether the landlord will give written consent for the new use.
  4. Get a fire safety check of the unit for the new use before you commit to the renovation design. Here is why a Pre-FSC check before renovation pays off.
  5. Make the lease conditional on approval, or agree a rent-free fit-out period long enough to cover it.

How Redguard helps

Redguard is a PE-led fire safety consultancy with 30+ years of combined experience. We handle both sides of a change of use: the planning or landlord application with URA, JTC or HDB, and the SCDF fire safety submission, through to the FSC. See our change of use service. We are a consultancy only and do not install or supply equipment, so our advice is independent of what your contractor sells.

Still choosing a unit? A Pre-FSC compliance check gives you a site survey and a written report for S$250, issued within 3 to 5 working days after the survey, and credited to your bill if you engage us for the submission.

WhatsApp us on 8332 1068 with the unit address, its current use and what you plan to use it for. We reply the same day.

Sources: URA: Changing the use of your property, SCDF: reminder to seek approval for change of use, SCDF: plans submission and fees, SCDF: FSC and TFP.

FAQ

Do I need URA approval and SCDF approval?

Usually yes. They check different things. URA, JTC or HDB decide whether the use is allowed there, and SCDF decides whether the layout is safe for that use.

My landlord says the unit is fine for my business. Is that enough?

No. Landlord consent is one part. Individual units with a different use must comply with the Fire Code standards and apply for their own FSC.

How long does a change of use take?

URA states about 10 working days for its part, if the submission is complete. The SCDF submission runs alongside it, and the FSC follows once the works are built and inspected.

Is changing part of my unit a change of use?

Yes. SCDF requires approval for a change of use of any part of a premises, such as turning a storeroom into a classroom.

Who can submit the change of use plans to SCDF?

A Qualified Person: a registered architect or Professional Engineer.

Need this for your premises?

Our team can help with Change of Use Approval: URA, JTC or HDB and SCDF.

View service

We use cookies to measure site visits and ad performance. You can opt out at any time in Cookie Settings.