How Long Does an SCDF FSC Application Take? A Step-by-Step Timeline

By REDGUARD Engineering Team 9 November 2026
Fire plan and safety plan signs mounted on a white wall

A step-by-step timeline for an SCDF Fire Safety Certificate in Singapore, from drawings to plan approval, works, inspection and the FSC, and how to avoid delays.

An FSC application has two halves: getting SCDF to approve the fire safety plans, then getting the FSC once the works are built and inspected. The paperwork side can move quickly. Most delays come from late starts, incomplete drawings, SCDF queries and works that don't match the approved plans.

If you have an opening date, the most useful thing you can do is start the fire safety submission before your contractor starts work, not after. Not sure whether you need one at all? Start with do I need an FSC for my shop, restaurant or office.

The timeline, step by step

StepWhat happensRedguard's target
1. Site survey and scopeWe visit the unit, confirm what it is approved for and what your works change.Included when you engage us for the submission
2. DrawingsWe prepare the fire safety plans for your review.Within 3 working days of your payment
3. Submission to SCDFOnce you approve the drawings, we submit them as Qualified Person.Within 3 working days of your approval
4. SCDF payment noticeSCDF issues the fee notice for the plan.Usually about 3 working days
5. Pay SCDF feeThe plan fee is paid so SCDF processes the submission.Within 2 to 3 working days
6. SCDF review and approvalSCDF reviews the plans and may raise queries, which we answer.Depends on complexity and queries
7. Fire safety worksYour contractor builds to the approved plans.Depends on your fit-out
8. Inspection and FSCA Registered Inspector inspects the completed works, then the FSC is applied for.After works are complete

Our overall target is to have the SCDF fee paid within 10 working days of your payment to us. That gets your submission into SCDF's queue about two weeks after you engage us. For the online application at step 8, see applying for an FSC online in Singapore.

For HDB premises the steps differ: PE-endorsed plans go to HDB, and lodgement typically takes about 7 working days, or about 14 working days for additions and alterations. See our HDB PE-endorsed plan submission service.

What if I need to open before the FSC?

SCDF can grant a Temporary Fire Permit (TFP) if the fire safety works are substantially complete and only very minor items are outstanding. The TFP lets you occupy the premises for a limited period, and the FSC must follow, usually within a maximum of 6 months. A TFP is not a shortcut around plan approval: the plans still need to be approved and the works built to them.

The five most common causes of delay

  1. Starting late. The contractor begins before plans are submitted, then has to redo work that SCDF doesn't accept. We cover this in renovating before SCDF approval.
  2. Missing information. Unclear layouts, missing room uses or no occupant load figures lead to SCDF queries.
  3. A change of use nobody spotted. If the new use differs from the approved use, the planning side (URA, JTC or HDB) may also need approval. See change of use approvals from URA, JTC, HDB and SCDF.
  4. Works that differ from the approved plans. Moved partitions or added rooms mean an amendment submission before the FSC.
  5. Slow decisions. Every day spent waiting for drawing approval or fee payment adds a day to the end date.

How to keep your project on schedule

  • Get a Pre-FSC compliance check before you sign the lease or finalise the design. You receive a written report within 3 to 5 working days after the site survey. Here is why it pays to check before you renovate.
  • Give your consultant the full layout and intended use at the start.
  • Approve drawings and pay the SCDF fee promptly.
  • Tell your consultant about any layout change during the works, before it is built.

How Redguard helps

Redguard is a PE-led fire safety consultancy with 30+ years of combined experience. We prepare and submit your SCDF plans, answer SCDF's queries and follow the application through to the FSC. We work to the step targets above on every BP, FP and MAA job, and we are a consultancy only, with no installation or equipment sales. See our Fire Safety Certificate service.

Have an opening date? WhatsApp us on 8332 1068 with your address and target date, and we'll tell you whether it's realistic and what to do first.

Sources: SCDF: FSC and TFP, SCDF: plans submission and fees, GoBusiness: TFP/FSC.

FAQ

How long does SCDF take to approve plans?

SCDF does not publish a fixed processing time. It depends on the size and complexity of the works and on whether queries are raised. Complete, clear drawings are the best way to keep it short.

Can the works start before SCDF approval?

Under the Fire Safety Act 1993, fire safety works need SCDF plan approval before they begin, unless they are exempt or fall under the minor additions and alterations (MAA) route.

How long do I have to get the FSC after a TFP?

Usually a maximum of 6 months, depending on the size, type and complexity of the project.

What does the SCDF plan fee cost?

SCDF's fee depends on the type of submission. For example, a change of use or additions and alterations with no increase in floor area is S$90 per storey. New fire safety works are charged by floor area. Our guide to FSC consultant costs lists the full SCDF fee table.

Is HDB faster?

HDB submissions of PE-endorsed plans follow a different route. Lodgement typically takes about 7 working days, and additions and alterations about 14 working days.

Need this for your premises?

Our team can help with Fire Safety Certificate (FSC) & SCDF Submission.

View service

We use cookies to measure site visits and ad performance. You can opt out at any time in Cookie Settings.