What an FSC consultant costs in Singapore: SCDF's own plan fees, what drives the professional fee, what a complete quote should include and how to compare quotes.
The cost of getting a Fire Safety Certificate has three parts: the consultant's professional fee, SCDF's own plan fee, and the cost of any fire safety works your contractor builds. The consultant's fee mostly depends on the size of the unit, whether it is a change of use, and how much the fire safety layout changes.
When you compare quotes, check what each one includes. A low quote that leaves out SCDF queries, amendments or the FSC application itself often ends up costing more.
1. SCDF's plan fee
SCDF charges a fee for each plan submission. The main rates are:
| Type of submission | SCDF fee |
|---|---|
| New fire safety works with prescribed fire safety measures | S$160 per 100 m² of floor area (or part) |
| New fire safety works without prescribed measures | S$100 per 100 m² (or part) |
| Change of use, or additions and alterations, with no increase in floor area | S$90 per storey |
| Amendment to approved works, no increase in floor area | S$90 per storey |
| New or A&A fire protection (FP) or mechanical ventilation (MV) works | S$90 per storey |
For a typical single-storey shop or office change of use, the SCDF plan fee is modest. The professional work is the larger part of the cost.
2. The consultant's fee: what drives it
- Change of use or not. A change of use usually needs a planning application (URA, JTC or HDB) as well as the SCDF submission. See change of use approvals from URA, JTC, HDB and SCDF.
- Floor area and layout. More rooms, exits and occupants mean more design and checking.
- Which plans are needed. Building plans (BP), fire protection plans (FP) such as sprinklers and alarms, or a simpler MAA lodgement for minor works.
- Special uses. Kitchens with suppression, storage of combustibles, high racking or larger occupant loads add requirements.
- Existing condition. If earlier works were never approved, they may need to be regularised first. Our case study on an HDB commercial unit audited after renovation shows how this happens.
3. What a complete quote should include
Ask whether the quote covers each of these. A full-service consultancy quote should:
- Site survey of the premises
- Fire safety drawings prepared and endorsed by a Qualified Person
- Submission to SCDF and, for HDB premises, to HDB
- Answering SCDF queries until approval
- The planning or landlord application for a change of use
- Coordination with your contractor during the works
- Support through inspection and the FSC application (see applying for an FSC online)
- A clear statement of what is not included (for example, SCDF fees, works, Registered Inspector fees)
At Redguard, the site survey is included when you engage us for the submission.
4. The cost of the works
The fire safety works themselves, such as sprinklers, alarms, emergency lighting, exit signs or kitchen suppression, are quoted separately by your contractor. A consultancy that does not sell equipment has no reason to over-specify, which helps keep this part in check. Starting the works before approval is the most expensive mistake; see renovating before SCDF approval.
How to compare quotes fairly
- Put each quote against the checklist above.
- Ask how SCDF queries and plan amendments are charged.
- Ask who the Qualified Person is and whether they are in-house. Only a registered architect or Professional Engineer can submit fire safety plans to SCDF; see who needs to apply for an SCDF FSC.
- Ask for the step-by-step timeline and what the consultant commits to. Ours is in how long an SCDF FSC application takes.
Not ready for a full quote?
If you are still deciding on a unit or a design, a Pre-FSC compliance check gives you a site survey and a written report for S$250, issued within 3 to 5 working days after the survey. If you then engage Redguard for the submission, the S$250 is credited to your bill. You can also try our free online FSC check first.
How Redguard helps
Redguard is a PE-led fire safety consultancy with 30+ years of combined experience and an in-house Professional Engineer. We prepare and submit SCDF and HDB plans, handle change of use applications with URA, JTC or HDB, and follow your application through to the FSC. We are a consultancy only and do not install or supply equipment.
For a quote, WhatsApp us on 8332 1068 with your address, floor area and what you plan to change. We reply the same day.
Sources: SCDF: plans submission and fees, SCDF: FSC and TFP.
FAQ
Is the SCDF fee included in a consultant's quote?
It depends on the consultant. Ask, because SCDF's plan fee is separate from the professional fee.
Why do quotes vary so much?
Scope. Some quotes cover drawings only, while others include SCDF queries, the change of use application and support through to the FSC.
Do I pay for the site survey?
At Redguard, the site survey is included when you engage us for the submission. A standalone Pre-FSC report (survey plus report) is S$250, credited if you go ahead.
Can a contractor do the submission instead?
Only a Qualified Person, a registered architect or Professional Engineer, can submit fire safety plans to SCDF. Many contractors subcontract this to a consultant. See who needs to apply for an SCDF FSC.
Does an HDB shop cost the same?
HDB premises need PE-endorsed plans submitted to HDB, which is a different route. Ask for a quote based on your unit, or see our HDB PE-endorsed plan submission service.
Need this for your premises?